Indian Railways has achieved a major breakthrough in the 6.59-kilometre-long Tunnel-14 of the Rishikesh-Karnaprayag Rail Project in Uttarakhand. The breakthrough, achieved in Rudraprayag district, connects the two excavated sections of the tunnel from Portal-1 at Sumerpur and Portal-2 at Marora.
The excavation comprises 4.7 kilometres from Portal-1 and 1.79 kilometres from Portal-2, marking an important milestone in the construction of the strategically significant rail project.
Specialised engineering measures ensure safe excavation
At Portal-1, a 110-metre stretch of the triple-track tunnel was excavated through loose soil beneath inhabited areas, with only 20 to 30 metres of soil and rock cover above it. Specialised techniques, including pre-excavation and multi-drifting, were employed to ensure safe construction.
At Portal-2, slope stabilisation measures included 30 to 35-metre-deep micropiles, 15 to 20-metre-long rock bolts and consolidation grouting. These interventions enabled the main tunnel excavation to begin in March 2024, after ground settlement issues at Marora and matters related to land and home acquisition were addressed.
Around 100 metres of mechanical excavation was also undertaken at Portal-2. Controlled blasting was carried out near both portals, strictly during daytime hours, to safeguard nearby settlements.
Specialised ventilation systems were deployed along the 4.7-kilometre excavation drive from Portal-1 to ensure fresh air circulation and regulate temperatures inside the tunnel.
Boost to connectivity in Uttarakhand
The breakthrough marks a significant step forward in the Rishikesh-Karnaprayag Rail Project, which aims to im.prove rail connectivity to the hill regions of Uttarakhand.
-PIB